Azha-1 Construction Updates - September 2024

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           61.09% Completed             38.91% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               543 Days

Time Remaining:                           310 Days

Project Status as of:                     30th September, 2024

Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
100%
1F Slab
100%
1F Column
100%
RF Slab
100%
Block Work
100%
Slab on Grade
100%
Plaster Work Interior
86.45%
Plaster Work Exterior
54.17%
Tiles Dry
48.99%
Tiles Wet
16.13%
Tiles Wall
14.4%
External Graphic
37.17%
External Paint
31.98%
False Ceiling Dry
20.17%
False Ceiling Wet
0.86%
Aluminium Work Frame
19.02%
Aluminium Work Glass
12.68%
Aluminium Work Shatter
8.93%