Azha-1 Construction Updates - September 2023
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 9.43% Completed 90.57% Remaining
Total Duration: 853 Days
Time Elapsed: 199 Days
Time Remaining: 654 Day
Project Status as of: 30th Sept, 2023
Excavation
94.81%
Soil Compaction
87.89%
Laying Road Base
82.99%
PCC
82.13%
Foundation
74.92%
Backfilling upto tie beam
20.74%