Azha-1 Construction Updates - October 2023

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           9.43% Completed             90.57% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               199 Days

Time Remaining:                           654 Day

Project Status as of:                     31st Oct, 2023

Excavation
94.81%
Soil Compaction
87.89%
Laying Road Base
82.99%
PCC
82.13%
Foundation
74.92%
Backfilling upto tie beam
20.74%
Previous slide