Azha-1 Construction Updates - May 2025
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 85.82% Completed 14.18% Remaining
Total Duration: 853 Days
Time Elapsed: 771 Days
Time Remaining: 82 Days
Project Status as of: 31st May, 2025
Roof Combo
99.71%
Dry Floor Tile
92.5%
Wet Floor Tile
79.25%
Wet Wall Tile
76.36%
Marble - Stair
65.7%
Paint - Int - 1st Coat Stucco
47.55%
Paint External
87.89%
False Ceiling Suspension Work
65.12%
False Ceiling Board Closing
41.21%
Aluminium Work Glass
79.25%
Metal Work - Stair
5.76%