Azha-1 Construction Updates - May 2024
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 54.54% Completed 45.46% Remaining
Total Duration: 853 Days
Time Elapsed: 412 Days
Time Remaining: 442 Day
Project Status as of: 31st May, 2024
Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
100%
1F Slab
100%
1F Column
100%
RF Slab
81.26%
Block Work
57%
Slab on Grade
90%