fbpx

Azha-1 Construction Updates - May 2024

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           54.54% Completed             45.46% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               412 Days

Time Remaining:                           442 Day

Project Status as of:                     31st May, 2024

Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
100%
1F Slab
100%
1F Column
100%
RF Slab
81.26%
Block Work
57%
Slab on Grade
90%
Previous slide
Next slide