Azha-1 Construction Updates - March 2024
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 41.53% Completed 58.47% Remaining
Total Duration: 853 Days
Time Elapsed: 346 Days
Time Remaining: 507 Day
Project Status as of: 31st March, 2024
Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
96%
GF Column
88%
1F Slab
82%
1F Column
75%
Roof Slab
69%
Block Work
18%
Slab on Grade
55%