fbpx

Azha-1 Construction Updates - March 2024

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           41.53% Completed             58.47% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               346 Days

Time Remaining:                           507 Day

Project Status as of:                     31st March, 2024

Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
96%
GF Column
88%
1F Slab
82%
1F Column
75%
Roof Slab
69%
Block Work
18%
Slab on Grade
55%
Previous slide
Next slide