Azha-1 Construction Updates - June 2023

Project Start Date:                       27th Dec, 2022

Forecast Finish Date:                  26th Dec, 2024

Progress Status:                           18.77% Completed             81.23% Remaining   

Total Duration:                              731 Days

Time Elapsed:                               216 Days

Time Remaining:                           515 Days

Site Works
100%
Sub Structure Concrete Works
100%
Super Structure Concrete Works
31.2%
Masonry Work
10.25%
Metal & Glass works
0%
Wooden Works
0%
Thermal & Moisture Protection Works
21.35%
Doors & Windows Works(Glazing)
0%
Wall Finishes
0.48%
Floor Finishes
0%
Ceiling Finishes
0%
Accessories Works
0%
Garbage Chute
0%
Elevator Works
0%
Mechanical Work
2.91%
Electrical Work
2.97%
Sanitary Fixtures
0%
Light Fittings
0%
ELV Systems
0%
Swimming Pool Works
0%
MEP Equipment's at Roof
0%
External Finishes Works
0%
External Works & Services
0%
Snagging Works
0%
Project Authorities Handover, Closeout
Project Authorities Handover, Closeout 0%