Azha-1 Construction Updates - June 2023
Project Start Date: 27th Dec, 2022
Forecast Finish Date: 26th Dec, 2024
Progress Status: 18.77% Completed 81.23% Remaining
Total Duration: 731 Days
Time Elapsed: 216 Days
Time Remaining: 515 Days
Site Works
100%
Sub Structure Concrete Works
100%
Super Structure Concrete Works
31.2%
Masonry Work
10.25%
Metal & Glass works
0%
Wooden Works
0%
Thermal & Moisture Protection Works
21.35%
Doors & Windows Works(Glazing)
0%
Wall Finishes
0.48%
Floor Finishes
0%
Ceiling Finishes
0%
Accessories Works
0%
Garbage Chute
0%
Elevator Works
0%
Mechanical Work
2.91%
Electrical Work
2.97%
Sanitary Fixtures
0%
Light Fittings
0%
ELV Systems
0%
Swimming Pool Works
0%
MEP Equipment's at Roof
0%
External Finishes Works
0%
External Works & Services
0%
Snagging Works
0%
Project Authorities Handover, Closeout
Project Authorities Handover, Closeout
0%