fbpx

Azha-1 Construction Updates - June 2024

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           61.57% Completed             38.43% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               467 Days

Time Remaining:                           386Day

Project Status as of:                     24th July, 2024

Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
100%
1F Slab
100%
1F Column
100%
RF Slab
100%
Block Work
80.69%
Slab on Grade
100%
Previous slide
Next slide