Azha-1 Construction Updates - June 2024
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 61.57% Completed 38.43% Remaining
Total Duration: 853 Days
Time Elapsed: 467 Days
Time Remaining: 386Day
Project Status as of: 24th July, 2024
Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
100%
1F Slab
100%
1F Column
100%
RF Slab
100%
Block Work
80.69%
Slab on Grade
100%
Previous slide
Next slide