Azha-1 Construction Updates - July 2023
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 4.54% Completed 95.46% Remaining
Total Duration: 853 Days
Time Elapsed: 108 Days
Time Remaining: 745 Day
Project Status as of: 31st July, 2023
Excavation
68%
Soil Compaction
66%
Laying Road Base
57%
PCC
36%
Foundation
21%
Backfilling upto tie beam
5%