Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 31.26% Completed 68.74% Remaining
Total Duration: 853 Days
Time Elapsed: 292 Days
Time Remaining: 561 Day
Project Status as of: 31st Jan, 2024
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Foundation
100%
Backfilling upto tie beam
86.33%