Azha-1 Construction Updates - December 2023

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           21.20% Completed             78.80% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               261 Days

Time Remaining:                           592 Day

Project Status as of:                     31st Dec, 2023

Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
97.11%
Foundation
95.1%
Backfilling upto tie beam
50.17%