Azha-1 Construction Updates - August 2023

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           6.10% Completed             93.9% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               139 Days

Time Remaining:                           714 Day

Project Status as of:                     31st Aug, 2023

Excavation
89.33%
Soil Compaction
85.87%
Laying Road Base
80.69%
PCC
61.09%
Foundation
44.38%
Backfilling upto tie beam
15.18%