Azha-1 Construction Updates - August 2023
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 6.10% Completed 93.9% Remaining
Total Duration: 853 Days
Time Elapsed: 139 Days
Time Remaining: 714 Day
Project Status as of: 31st Aug, 2023
Excavation
89.33%
Soil Compaction
85.87%
Laying Road Base
80.69%
PCC
61.09%
Foundation
44.38%
Backfilling upto tie beam
15.18%