Azha-1 Construction Updates - April 2025

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           82.98% Completed             17.02% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               747 Days

Time Remaining:                           106 Days

Project Status as of:                     30th April, 2025

Roof Combo
95.67%
Dry Floor Tile
92.21%
Wet Floor Tile
70.6%
Wet Wall Tile
65.41%
Marble - Stair
60.51%
Paint - Int - 1st Coat Stucco
43.22%
Paint External
87.89%
False Ceiling Suspension Work
65.12%
False Ceiling Board Clsoing
37.17%
Aluminium Work Glass
78.38%
Wooden Door - Int
41.78%
Kitchen Cabinet
33.71%
Roof Access hatch
26.8%
Main Gate
23.91%
Fence
17.57%

Streets View & Roadworks Progress