Azha-1 Construction Updates - April 2025
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 82.98% Completed 17.02% Remaining
Total Duration: 853 Days
Time Elapsed: 747 Days
Time Remaining: 106 Days
Project Status as of: 30th April, 2025
Roof Combo
95.67%
Dry Floor Tile
92.21%
Wet Floor Tile
70.6%
Wet Wall Tile
65.41%
Marble - Stair
60.51%
Paint - Int - 1st Coat Stucco
43.22%
Paint External
87.89%
False Ceiling Suspension Work
65.12%
False Ceiling Board Clsoing
37.17%
Aluminium Work Glass
78.38%
Wooden Door - Int
41.78%
Kitchen Cabinet
33.71%
Roof Access hatch
26.8%
Main Gate
23.91%
Fence
17.57%