Azha-1 Construction Updates - APRIL 2024

Project Start Date:                       15th April, 2023

Forecast Finish Date:                  14th Aug, 2025

Progress Status:                           49.16% Completed             50.84% Remaining   

Total Duration:                              853 Days

Time Elapsed:                               371 Days

Time Remaining:                           482 Day

Project Status as of:                     30th April, 2024

Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
93%
1F Slab
86%
1F Column
79%
Roof Slab
72%
Block Work
21%
Slab on Grade
67%