Azha-1 Construction Updates - APRIL 2024
Project Start Date: 15th April, 2023
Forecast Finish Date: 14th Aug, 2025
Progress Status: 49.16% Completed 50.84% Remaining
Total Duration: 853 Days
Time Elapsed: 371 Days
Time Remaining: 482 Day
Project Status as of: 30th April, 2024
Mobilization
95%
Excavation
100%
Soil Compaction
100%
Laying Road Base
100%
PCC
100%
Casting Foundation
100%
Tie beam
100%
GF Column
93%
1F Slab
86%
1F Column
79%
Roof Slab
72%
Block Work
21%
Slab on Grade
67%